Installation Process

Clear milestones, predictable timelines.

  1. 1

    Site assessment & shading study

    ~1–2 hrs

    Laser/phone LiDAR, roof scan, tilt/azimuth capture and horizon mask. Shading losses measured with seasonal impact.

    Output: Assessment report & photo log
  2. 2

    System sizing & engineering design

    1–2 days

    PVsyst yield estimate, stringing, conductor sizing, earthing & lightning protection. Structural checks for wind uplift.

    Output: Single-line diagram (SLD) & BOM
  3. 3

    Permits, net-metering, DISCOM approvals

    3–10 days*

    We prepare and file all forms, drawings and proofs. Follow-ups handled end-to-end.

    Output: Approval & inspection slot
  4. 4

    Mounting, wiring, safety checks

    1–3 days

    Anchors/rails fixed, panels mounted, MC4 terminations, DC/AC dressing, earthing & SPD. Safety toolbox talk daily.

    Output: Installed array & tidy rooftop
  5. 5

    Testing, commissioning, documentation

    Half day

    IV-curve, insulation & polarity tests. Inverter config, Wi-Fi/monitoring, handover and user training.

    Output: Test reports & warranty kit
  6. *Approval windows vary by DISCOM and inspection backlog.

On-site installation in progress
Safety-first crewTier-1 hardwareDISCOM compliantMonitoring app
Install detail 1
Install detail 2
Install detail 3

What we handle

So you don’t have to chase vendors, approvals or paperwork.

Load study & ROI projection

DISCOM/CEA compliant drawings

Material logistics & site safety

Scaffold/boom as required

Monitoring app setup

AMC & cleaning plans

Installation FAQs

Short answers to common questions.

How long does a typical 5–10 kW rooftop take?

Survey and design in 1–2 days, approvals vary by DISCOM (3–10 days). On-site install is usually 1–2 days, commissioning the same day.

Will drilling damage my roof?

We use correct anchors & sealants for RCC/tile/tin. All penetrations are sealed and water-tested, with workmanship warranty.

What tests are done before handover?

Insulation resistance, polarity, IV-curve (where applicable), string voltages, earthing & SPD checks, and live yield verification.

Do you set up the monitoring app?

Yes — owner login, alert thresholds and basic training are part of commissioning. We also offer AMC with periodic cleaning.

Book a site visit